ROADWORK EVENT SUMMARY
Tilton Road, Birmingham between 24 Sep and 17 Oct 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Tilton Road, Birmingham

Severn Trent Water carried out Utility repair and maintenance works on Tilton Road, Birmingham.

These works were categorised as Urgent Works with an immediate start.

The road was closed for some or all of the period.

The works were originally planned between 24 Sep 2024 and 18 Oct 2024 and were actually completed between 24 Sep 2024 (10:00) and 17 Oct 2024 (08:00). The works impacted the carriageway only.

The information for these works was last updated by Severn Trent Water on 17 October 2024 at 08:50.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Tilton Road, Birmingham

Works Details

WORKS COMPLETED
Immediate - urgent
Severn Trent Water logo
These works are handled by:
Severn Trent Water
Birmingham City Council logo
Local Authority:
Birmingham City Council
Works Reference LB7012201-000013801225
Permit Number 01
Place Name Tilton Road
Birmingham
Proposed Start 24 Sep 2024
Proposed End 18 Oct 2024
Actual Start 24 Sep 2024 10:00
Actual End 17 Oct 2024 08:00
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
52.475877
-1.865891
Last Updated 17 Oct 2024 08:50
Contact Details for Activity LB7012201-000013801225 (Tilton Road, Birmingham)

In the event that you have an issue with these works, please contact Severn Trent Water, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Birmingham City Council that authorised the works.

It would assist the organisations if you quote the work reference number of LB7012201-000013801225.

Works History for Activity LB7012201-000013801225 (Tilton Road, Birmingham)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Sep 2024
11:37
Work Started
24 Sep 2024
11:00
7 Oct 2024
17:00
24 Sep 2024
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Sep 2024
14:00
Permit Granted
24 Sep 2024
11:00
7 Oct 2024
17:00
24 Sep 2024
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Sep 2024
15:50
Permit Alteration Granted
24 Sep 2024
11:00
7 Oct 2024
17:00
24 Sep 2024
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Oct 2024
14:09
Permit Alteration Granted
24 Sep 2024
11:00
11 Oct 2024
17:00
24 Sep 2024
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Oct 2024
15:16
Permit Alteration Granted
24 Sep 2024
11:00
18 Oct 2024
17:00
24 Sep 2024
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Oct 2024
09:50
Work Stopped
24 Sep 2024
11:00
18 Oct 2024
17:00
24 Sep 2024
11:00
17 Oct 2024
09:00
Completed

Works Permits for Tilton Road, Birmingham

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.