ROADWORK EVENT SUMMARY
Lee Lane, Heanor between 21 Oct and 28 Dec 2024

Works Description for Lee Lane, Heanor

Severn Trent Water were proposing to carry out Utility repair and maintenance works on Lee Lane, Heanor.

These works were categorised as Major.

There were no traffic signals or road closures necessary for these works and traffic would have operated on a give-and-take basis. However, the works were cancelled.

The works were originally planned to start 21 October 2024 and run through until 28 December 2024. The works were due to impact the footway and carriageway.

The information for these works was last updated by Severn Trent Water on 24 October 2024 at 15:14.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Lee Lane, Heanor

Works Details

WORKS CANCELLED
Major
Severn Trent Water logo
These works are handled by:
Severn Trent Water
Derbyshire County Council logo
Local Authority:
Derbyshire County Council
Works Reference LB53216151-SO1-2
Permit Number 02
Place Name Lee Lane
Heanor
Proposed Start 21 Oct 2024
Proposed End 28 Dec 2024
Actual Start
Actual End
Traffic Management Give and take
Impact Footway, Carriageway
Coordinates
Lat, Lon
53.0123
-1.329587
Last Updated 24 Oct 2024 15:14
Works History for Activity LB53216151-SO1-2 (Lee Lane, Heanor)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
8 Oct 2024
14:47
Permit Submitted
21 Oct 2024
01:00
28 Dec 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Oct 2024
14:09
Permit Granted
21 Oct 2024
01:00
28 Dec 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Oct 2024
16:14
Permit Cancelled
21 Oct 2024
01:00
28 Dec 2024
00:00
Cancelled

Works Permits for Lee Lane, Heanor

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT08b (Manual control of traffic management)

For the activities hereby permitted, it is a condition of this permit that, for the traffic management deployed (state type), it is manually operated between (x hours and y hours).

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.