ROADWORK EVENT SUMMARY
A442 From Fenn Green Junction To Dodds Green Cottage, Fenn Green, Alveley between 23 Oct 2023 and 20 Dec 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for A442 From Fenn Green Junction To Dodds Green Cottage, Fenn Green, Alveley

Severn Trent Water are carrying out Utility asset works on A442 From Fenn Green Junction To Dodds Green Cottage, Fenn Green, Alveley.

These works are categorised as Major.

The works should not impact the carriageway.

The works started on 23 October 2023 at 07:00 and could run through until 20 December 2024. The works will impact the verge only.

The information for these works was last updated by Severn Trent Water on 11 November 2024 at 11:35.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for A442 From Fenn Green Junction To Dodds Green Cottage, Fenn Green, Alveley

Works Details

WORKS IN PROGRESS
Major
Severn Trent Water logo
These works are handled by:
Severn Trent Water
Shropshire Council logo
Local Authority:
Shropshire Council
Works Reference LB525A7W13487002
Permit Number 02
Place Name A442 From Fenn Green Junction To Dodds Green Cottage
Fenn Green
Alveley
Proposed Start 20 Oct 2023
Proposed End 20 Dec 2024
Actual Start 23 Oct 2023 07:00
Actual End
Traffic Management No carriageway incursion
Impact Verge
Coordinates
Lat, Lon
52.448019
-2.338026
Last Updated 11 Nov 2024 11:35
Works History for Activity LB525A7W13487002 (A442 From Fenn Green Junction To Dodds Green Cottage, Fenn Green, Alveley)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
10 Oct 2023
15:07
Permit Submitted
16 Oct 2023
07:00
31 Jul 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Oct 2023
08:39
Permit Alteration Granted
20 Oct 2023
07:00
31 Jul 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Oct 2023
09:31
Permit Granted
20 Oct 2023
07:00
31 Jul 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Oct 2023
09:58
Work Started
20 Oct 2023
07:00
31 Jul 2024
18:00
23 Oct 2023
07:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
31 Jul 2024
10:35
Permit Alteration Granted
20 Oct 2023
08:00
31 Oct 2024
18:00
23 Oct 2023
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Nov 2024
11:35
Permit Alteration Granted
20 Oct 2023
08:00
20 Dec 2024
18:00
23 Oct 2023
08:00
In Progress

Works Permits for A442 From Fenn Green Junction To Dodds Green Cottage, Fenn Green, Alveley

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.