ROADWORK EVENT SUMMARY
Gaythorn Street, Salford between 14 Feb 2022 and 28 Feb 2025

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Gaythorn Street, Salford

Salford City Council are carrying out Highway improvement works on Gaythorn Street, Salford.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 14 February 2022 at 00:00 and could run through until 28 February 2025. The works will impact the carriageway only.

The information for these works was last updated by Salford City Council on 14 October 2024 at 10:51.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Gaythorn Street, Salford

Works Details

WORKS IN PROGRESS
Major
Salford City Council logo
These works are handled by:
Salford City Council
Salford City Council logo
Local Authority:
Salford City Council
Works Reference KS0043021294
Permit Number 02
Place Name Gaythorn Street
Salford
Proposed Start 14 Feb 2022
Proposed End 28 Feb 2025
Actual Start 14 Feb 2022 00:00
Actual End
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
53.481902
-2.265182
Last Updated 14 Oct 2024 10:51
Works History for Activity KS0043021294 (Gaythorn Street, Salford)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Mar 2022
16:00
Permit Submitted
9 Jun 2022
00:00
10 Oct 2024
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Mar 2022
10:00
Permit Alteration Granted
14 Feb 2022
00:00
4 Oct 2024
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Mar 2022
16:29
Permit Granted
14 Feb 2022
00:00
4 Oct 2024
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Apr 2022
11:00
Work Started
14 Feb 2022
00:00
4 Oct 2024
23:59
14 Feb 2022
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Oct 2024
11:51
Permit Alteration Granted
14 Feb 2022
00:00
28 Feb 2025
23:59
14 Feb 2022
00:00
In Progress

Works Permits for Gaythorn Street, Salford

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT04a (Removal of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that all remaining excavated or stored backfill materials and/or any unemployed plant must be removed from the public highway within (x hours e.g. 24) or by the stipulated time (e.g. at the end of the working day or prior to the site being un-occupied) due to (stipulate reason for application of condition).

+
NCT04b (Storage of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that no materials and/or plant that will not be utilised within the working day are to be stored within or outside of the defined working space from (insert date) until (insert date) due to (stipulate reason for application of condition).

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT09b (Traffic management arrangements to be in place)

For the activities hereby permitted, it is a condition of this permit that the works comprised in [specified part A/B] of the activities hereby permitted shall be subject to and shall occur only when the following traffic management measures are in place [or as attached in schedule.].

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.