ROADWORK EVENT SUMMARY
Wood Lane, Sonning Common, Reading between 8 and 10 Oct 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Wood Lane, Sonning Common, Reading

Oxfordshire County Council carried out Highway improvement works on Wood Lane, Sonning Common, Reading.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 8 Oct 2024 and 10 Oct 2024 and were actually completed between 8 Oct 2024 (22:00) and 10 Oct 2024 (06:00). The works impacted the carriageway only.

The information for these works was last updated by Oxfordshire County Council on 10 October 2024 at 09:12.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Wood Lane, Sonning Common, Reading

Works Details

WORKS COMPLETED
Major
Oxfordshire County Council logo
These works are handled by:
Oxfordshire County Council
Oxfordshire County Council logo
Local Authority:
Oxfordshire County Council
Works Reference KE40076917128
Permit Number 02
Place Name Wood Lane
Sonning Common
Reading
Proposed Start 8 Oct 2024
Proposed End 10 Oct 2024
Actual Start 8 Oct 2024 22:00
Actual End 10 Oct 2024 06:00
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
51.514035
-0.985155
Last Updated 10 Oct 2024 09:12
Works History for Activity KE40076917128 (Wood Lane, Sonning Common, Reading)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Sep 2024
14:02
Permit Submitted
8 Oct 2024
21:00
10 Oct 2024
07:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Sep 2024
16:04
Permit Granted
8 Oct 2024
21:00
10 Oct 2024
07:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Oct 2024
09:36
Work Started
8 Oct 2024
21:00
10 Oct 2024
07:00
8 Oct 2024
23:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
10 Oct 2024
10:12
Work Stopped
8 Oct 2024
21:00
10 Oct 2024
07:00
8 Oct 2024
23:00
10 Oct 2024
07:00
Completed

Works Permits for Wood Lane, Sonning Common, Reading

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT04a (Removal of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that all remaining excavated or stored backfill materials and/or any unemployed plant must be removed from the public highway within (x hours e.g. 24) or by the stipulated time (e.g. at the end of the working day or prior to the site being un-occupied) due to (stipulate reason for application of condition).

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.