ROADWORK EVENT SUMMARY
Bank Bridge Road, Manchester between 7 Oct and 8 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Bank Bridge Road, Manchester

Electricity North West (NorWeb) carried out Diversionary works on Bank Bridge Road, Manchester.

These works were categorised as Major.

Multi-way signals were in place for some or all of the period.

The works were originally planned between 7 Oct 2024 and 8 Nov 2024 and were actually completed between 7 Oct 2024 (16:35) and 8 Nov 2024 (16:50). The works impacted the footway and carriageway.

The information for these works was last updated by Electricity North West (NorWeb) on 11 November 2024 at 07:47.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Bank Bridge Road, Manchester

Works Details

WORKS COMPLETED
Major
Electricity North West (NorWeb) logo
These works are handled by:
Electricity North West (NorWeb)
Manchester City Council logo
Local Authority:
Manchester City Council
Works Reference JG202NP_CAP-50017906_O
Permit Number 02
Place Name Bank Bridge Road
Manchester
Proposed Start 7 Oct 2024
Proposed End 8 Nov 2024
Actual Start 7 Oct 2024 16:35
Actual End 8 Nov 2024 16:50
Traffic Management Multi-way signals
Impact Footway, Carriageway
Coordinates
Lat, Lon
53.491555
-2.186019
Last Updated 11 Nov 2024 07:47
Works History for Activity JG202NP_CAP-50017906_O (Bank Bridge Road, Manchester)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Sep 2024
16:01
Permit Submitted
11 Oct 2024
01:00
14 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Oct 2024
15:00
Permit Alteration Granted
7 Oct 2024
01:00
8 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Oct 2024
09:26
Permit Granted
7 Oct 2024
01:00
8 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
8 Oct 2024
09:54
Work Started
7 Oct 2024
01:00
8 Nov 2024
00:00
7 Oct 2024
17:35
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
8 Oct 2024
10:21
Permit Alteration Granted
7 Oct 2024
01:00
8 Nov 2024
00:00
7 Oct 2024
17:35
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Nov 2024
07:47
Work Stopped
7 Oct 2024
01:00
8 Nov 2024
00:00
7 Oct 2024
17:35
8 Nov 2024
16:50
Completed

Works Permits for Bank Bridge Road, Manchester

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT08b (Manual control of traffic management)

For the activities hereby permitted, it is a condition of this permit that, for the traffic management deployed (state type), it is manually operated between (x hours and y hours).

+
NCT09c (Signal removal from operation when no longer required)

This condition is attached to permits in cases where temporary traffic signals are used. For the activities hereby permitted, it is a condition of this permit that activities using portable traffic signals must have the signals (whether manually operated or not) removed from use as soon as possible and no later than four hours after completion of works irrespective of day of completion.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.