ROADWORK EVENT SUMMARY
Kings Road South, Wallsend between 9 Aug and 3 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Kings Road South, Wallsend

Northern Powergrid (Northeast) carried out Utility asset works on Kings Road South, Wallsend.

These works were categorised as Major.

Multi-way signals were in place for some or all of the period.

The works were originally planned between 9 Aug 2024 and 22 Nov 2024 and were actually completed between 9 Aug 2024 (09:30) and 3 Nov 2024 (15:00). The works impacted the footway and carriageway.

The information for these works was last updated by Northern Powergrid (Northeast) on 4 November 2024 at 08:37.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Kings Road South, Wallsend

Works Details

WORKS COMPLETED
Major
Northern Powergrid (Northeast) logo
These works are handled by:
Northern Powergrid (Northeast)
North Tyneside Council logo
Local Authority:
North Tyneside Council
Works Reference JD707NC81305-V
Permit Number 02
Place Name Kings Road South
Wallsend
Proposed Start 9 Aug 2024
Proposed End 22 Nov 2024
Actual Start 9 Aug 2024 09:30
Actual End 3 Nov 2024 15:00
Traffic Management Multi-way signals
Impact Footway, Carriageway
Coordinates
Lat, Lon
54.998717
-1.534133
Last Updated 4 Nov 2024 08:37
Works History for Activity JD707NC81305-V (Kings Road South, Wallsend)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Jun 2024
13:34
Permit Submitted
2 Aug 2024
01:00
1 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Jun 2024
09:08
Permit Alteration Granted
2 Aug 2024
01:00
1 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Jun 2024
10:28
Permit Granted
2 Aug 2024
01:00
1 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Jul 2024
15:44
Permit Alteration Granted
9 Aug 2024
01:00
22 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Aug 2024
11:35
Work Started
9 Aug 2024
01:00
22 Oct 2024
01:00
9 Aug 2024
10:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Oct 2024
10:51
Permit Alteration Granted
9 Aug 2024
01:00
22 Nov 2024
00:00
9 Aug 2024
10:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Nov 2024
08:37
Work Stopped
9 Aug 2024
01:00
22 Nov 2024
00:00
9 Aug 2024
10:30
3 Nov 2024
15:00
Completed

Works Permits for Kings Road South, Wallsend

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT09b (Traffic management arrangements to be in place)

For the activities hereby permitted, it is a condition of this permit that the works comprised in [specified part A/B] of the activities hereby permitted shall be subject to and shall occur only when the following traffic management measures are in place [or as attached in schedule.].

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.