ROADWORK EVENT SUMMARY
The Links, Whitley Bay between 4 Oct 2024 and 2 Oct 2025

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for The Links, Whitley Bay

This is a PAA (Provisional Advance Authorisation) permit that has been granted before final details of an activity have been finalised. A full permit will be required before activities can commence.


North Tyneside Council were proposing to carry out Highway repair and maintenance works on The Links, Whitley Bay.

These works were categorised as Major.

Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.

The works were originally planned to start 4 October 2024 and run through until 2 October 2025. The works were due to impact the footway, carriageway, verge, cycleway and footpath.

The information for these works was last updated by North Tyneside Council on 16 August 2024 at 13:22.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for The Links, Whitley Bay

Works Details

WORKS CANCELLED
Major (PAA)
North Tyneside Council logo
These works are handled by:
North Tyneside Council
North Tyneside Council logo
Local Authority:
North Tyneside Council
Works Reference HY003S000000003302
Permit Number 01
Place Name The Links
Whitley Bay
Proposed Start 4 Oct 2024
Proposed End 2 Oct 2025
Actual Start
Actual End
Traffic Management Multi-way signals
Impact Footway, Carriageway, Verge, Cycleway, Footpath
Coordinates
Lat, Lon
55.056582
-1.453486
Last Updated 16 Aug 2024 13:22
Works History for Activity HY003S000000003302 (The Links, Whitley Bay)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Jul 2024
11:02
Permit Submitted
4 Oct 2024
01:00
2 Oct 2025
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Jul 2024
11:04
Permit Granted
4 Oct 2024
01:00
2 Oct 2025
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Aug 2024
14:22
Permit Cancelled
4 Oct 2024
01:00
2 Oct 2025
01:00
Cancelled

Works Permits for The Links, Whitley Bay

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.