ROADWORK EVENT SUMMARY
Leabrook Road, Wednesbury between 29 Jul and 6 Oct 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Leabrook Road, Wednesbury

Western Power Distribution (West Midlands) are carrying out New service connection on Leabrook Road, Wednesbury.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 29 July 2024 at 13:24 and could run through until 6 October 2024. The works will impact the footway and carriageway.

The information for these works was last updated by Western Power Distribution (West Midlands) on 27 August 2024 at 07:58.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Leabrook Road, Wednesbury

Works Details

WORKS IN PROGRESS
Major
Western Power Distribution (West Midlands) logo
These works are handled by:
Western Power Distribution (West Midlands)
Sandwell Metropolitan Borough Council logo
Local Authority:
Sandwell Metropolitan Borough Council
Works Reference HM7252462100D
Permit Number 02
Place Name Leabrook Road
Wednesbury
Proposed Start 29 Jul 2024
Proposed End 6 Oct 2024
Actual Start 29 Jul 2024 13:24
Actual End
Traffic Management Multi-way signals
Impact Footway, Carriageway
Coordinates
Lat, Lon
52.54637
-2.034766
Last Updated 27 Aug 2024 07:58
Contact Details for Activity HM7252462100D (Leabrook Road, Wednesbury)

In the event that you have an issue with these works, please contact Western Power Distribution (West Midlands), the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Sandwell Metropolitan Borough Council that authorised the works.

It would assist the organisations if you quote the work reference number of HM7252462100D.

Sandwell Metropolitan Borough Council
Telephone0121 368 1177
Works History for Activity HM7252462100D (Leabrook Road, Wednesbury)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
2 Jul 2024
10:08
Permit Submitted
15 Jul 2024
01:00
12 Aug 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Jul 2024
15:07
Permit Alteration Granted
15 Jul 2024
01:00
12 Aug 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Jul 2024
13:19
Permit Granted
15 Jul 2024
01:00
12 Aug 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Jul 2024
13:19
Permit Alteration Granted
15 Jul 2024
01:00
12 Aug 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Jul 2024
15:00
Permit Alteration Granted
29 Jul 2024
01:00
26 Aug 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
29 Jul 2024
15:29
Work Started
29 Jul 2024
01:00
26 Aug 2024
00:59
29 Jul 2024
14:24
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Aug 2024
08:58
Permit Alteration Granted
29 Jul 2024
01:00
7 Oct 2024
00:59
29 Jul 2024
14:24
In Progress

Works Permits for Leabrook Road, Wednesbury

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT03 (Activities ancillary to those permitted - supplementary information)

For the activities hereby permitted, it is a condition of this permit that, if there are changes to ancillary activities, either in the street to which the application relates or in an adjacent street that become known about within the duration of the permit, the authority must be notified.

+
NCT08b (Manual control of traffic management)

For the activities hereby permitted, it is a condition of this permit that, for the traffic management deployed (state type), it is manually operated between (x hours and y hours).

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.