ROADWORK EVENT SUMMARY
Queen Street, Chesterton, Newcastle Under Lyme between 13 and 26 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Queen Street, Chesterton, Newcastle Under Lyme

Western Power Distribution (West Midlands) are carrying out New service connection on Queen Street, Chesterton, Newcastle Under Lyme.

The works started on 13 November 2024 at 12:07 and could run through until 26 November 2024. The works will impact the footway and carriageway.

The information for these works was last updated by Western Power Distribution (West Midlands) on 13 November 2024 at 13:11.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Queen Street, Chesterton, Newcastle Under Lyme

Works Details

WORKS IN PROGRESS
Western Power Distribution (West Midlands) logo
These works are handled by:
Western Power Distribution (West Midlands)
Staffordshire County Council logo
Local Authority:
Staffordshire County Council
Works Reference HM5222473170B
Permit Number 01
Place Name Queen Street
Chesterton
Newcastle Under Lyme
Proposed Start 13 Nov 2024
Proposed End 26 Nov 2024
Actual Start 13 Nov 2024 12:07
Actual End
Traffic Management Some carriageway incursion
Impact Footway, Carriageway
Coordinates
Lat, Lon
53.0411
-2.25108
Last Updated 13 Nov 2024 13:11
Works History for Activity HM5222473170B (Queen Street, Chesterton, Newcastle Under Lyme)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
26 Sep 2024
11:40
Permit Submitted
13 Nov 2024
00:00
26 Nov 2024
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Oct 2024
13:40
Permit Alteration Granted
13 Nov 2024
00:00
26 Nov 2024
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Oct 2024
15:27
Permit Granted
13 Nov 2024
00:00
26 Nov 2024
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Oct 2024
12:34
Permit Alteration Granted
13 Nov 2024
00:00
26 Nov 2024
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
13 Nov 2024
13:11
Work Started
13 Nov 2024
00:00
26 Nov 2024
23:59
13 Nov 2024
12:07
In Progress

Works Permits for Queen Street, Chesterton, Newcastle Under Lyme

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT09a (Changes to traffic management arrangements)

For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.