ROADWORK EVENT SUMMARY
Home Park Road, Wimbledon on 20 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Home Park Road, Wimbledon

London Borough Of Merton carried out Highway repair and maintenance works on Home Park Road, Wimbledon.

The works were originally planned between 20 Nov 2024 and 22 Nov 2024 and were actually completed on 20 Nov 2024 between 11:33 and 11:48. The works impacted the footway only.

The information for these works was last updated by London Borough Of Merton on 20 November 2024 at 12:00.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Home Park Road, Wimbledon

Works Details

WORKS COMPLETED
London Borough Of Merton logo
These works are handled by:
London Borough Of Merton
London Borough Of Merton logo
Local Authority:
London Borough Of Merton
Works Reference HC00146432113
Permit Number 01
Place Name Home Park Road
Wimbledon
Proposed Start 20 Nov 2024
Proposed End 22 Nov 2024
Actual Start 20 Nov 2024 11:33
Actual End 20 Nov 2024 11:48
Traffic Management Some carriageway incursion
Impact Footway
Coordinates
Lat, Lon
51.434612
-0.200576
Last Updated 20 Nov 2024 12:00
Works History for Activity HC00146432113 (Home Park Road, Wimbledon)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Nov 2024
11:43
Permit Submitted
20 Nov 2024
00:00
22 Nov 2024
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Nov 2024
12:18
Permit Granted
20 Nov 2024
00:00
22 Nov 2024
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Nov 2024
11:41
Work Started
20 Nov 2024
00:00
22 Nov 2024
23:59
20 Nov 2024
11:33
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Nov 2024
12:00
Work Stopped
20 Nov 2024
00:00
22 Nov 2024
23:59
20 Nov 2024
11:33
20 Nov 2024
11:48
Completed

Works Permits for Home Park Road, Wimbledon

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.