ROADWORK EVENT SUMMARY
Wainwright Grove, Liverpool between 24 Sep and 11 Oct 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Wainwright Grove, Liverpool

ManWeb carried out Utility repair and maintenance works on Wainwright Grove, Liverpool.

These works were categorised as Major.

Multi-way signals were in place for some or all of the period.

The works were originally planned between 24 Sep 2024 and 11 Oct 2024 and were actually completed between 24 Sep 2024 (12:00) and 11 Oct 2024 (17:30). The works impacted the carriageway only.

The information for these works was last updated by ManWeb on 11 October 2024 at 20:42.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Wainwright Grove, Liverpool

Works Details

WORKS COMPLETED
Major
ManWeb logo
These works are handled by:
ManWeb
Liverpool City Council logo
Local Authority:
Liverpool City Council
Works Reference GY030DTHJT4079A
Permit Number 03
Place Name Wainwright Grove
Liverpool
Proposed Start 24 Sep 2024
Proposed End 11 Oct 2024
Actual Start 24 Sep 2024 12:00
Actual End 11 Oct 2024 17:30
Traffic Management Multi-way signals
Impact Carriageway
Coordinates
Lat, Lon
53.356223
-2.903291
Last Updated 11 Oct 2024 20:42
Works History for Activity GY030DTHJT4079A (Wainwright Grove, Liverpool)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Feb 2024
13:50
Permit Submitted
2 Apr 2024
01:00
19 Apr 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Feb 2024
13:16
Permit Granted
2 Apr 2024
01:00
19 Apr 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Mar 2024
14:38
Permit Alteration Granted
13 Aug 2024
01:00
30 Aug 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Jul 2024
10:09
Permit Alteration Granted
24 Sep 2024
01:00
11 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Sep 2024
13:06
Work Started
24 Sep 2024
01:00
11 Oct 2024
01:00
24 Sep 2024
13:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Oct 2024
21:42
Work Stopped
24 Sep 2024
01:00
11 Oct 2024
01:00
24 Sep 2024
13:00
11 Oct 2024
18:30
Completed

Works Permits for Wainwright Grove, Liverpool

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT04a (Removal of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that all remaining excavated or stored backfill materials and/or any unemployed plant must be removed from the public highway within (x hours e.g. 24) or by the stipulated time (e.g. at the end of the working day or prior to the site being un-occupied) due to (stipulate reason for application of condition).

+
NCT04b (Storage of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that no materials and/or plant that will not be utilised within the working day are to be stored within or outside of the defined working space from (insert date) until (insert date) due to (stipulate reason for application of condition).

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.