ROADWORK EVENT SUMMARY
Town Hill, Bewsey And Whitecross, Warrington between 19 Dec 2024 and 3 Jan 2025

Works Description for Town Hill, Bewsey And Whitecross, Warrington

ManWeb are carrying out Utility repair and maintenance works on Town Hill, Bewsey And Whitecross, Warrington.

These works are categorised as Urgent Works with an immediate start.

The works should not impact the carriageway.

The works started on 19 December 2024 at 17:29 and could run through until 3 January 2025. The works will impact the footway only.

The information for these works was last updated by ManWeb on 20 December 2024 at 08:17.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Town Hill, Bewsey And Whitecross, Warrington

Works Details

WORKS IN PROGRESS
Immediate - urgent
ManWeb logo
These works are handled by:
ManWeb
Warrington Borough Council logo
Local Authority:
Warrington Borough Council
Works Reference GY004581512R
Permit Number 01
Place Name Town Hill
Bewsey And Whitecross
Warrington
Proposed Start 19 Dec 2024
Proposed End 3 Jan 2025
Actual Start 19 Dec 2024 17:29
Actual End
Traffic Management No carriageway incursion
Impact Footway
Coordinates
Lat, Lon
53.390145
-2.592351
Last Updated 20 Dec 2024 08:17
Works History for Activity GY004581512R (Town Hill, Bewsey And Whitecross, Warrington)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Dec 2024
17:59
Permit Submitted
19 Dec 2024
17:29
3 Jan 2025
00:00
19 Dec 2024
17:29
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Dec 2024
08:17
Permit Granted
19 Dec 2024
17:29
3 Jan 2025
00:00
19 Dec 2024
17:29
In Progress

Works Permits for Town Hill, Bewsey And Whitecross, Warrington

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.