ROADWORK EVENT SUMMARY
Morris Lane, Kirkstall, Leeds between 19 Feb and 28 Mar 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Morris Lane, Kirkstall, Leeds

Leeds City Council carried out Highway repair and maintenance works on Morris Lane, Kirkstall, Leeds.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 19 Feb 2024 and 2 Apr 2024 and were actually completed between 19 Feb 2024 (09:30) and 28 Mar 2024 (15:00). The works impacted the carriageway only.

The information for these works was last updated by Leeds City Council on 28 March 2024 at 15:17.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Morris Lane, Kirkstall, Leeds

Works Details

WORKS COMPLETED
Major
Leeds City Council logo
These works are handled by:
Leeds City Council
Leeds City Council logo
Local Authority:
Leeds City Council
Works Reference GP00658575700
Permit Number 02
Place Name Morris Lane
Kirkstall
Leeds
Proposed Start 19 Feb 2024
Proposed End 2 Apr 2024
Actual Start 19 Feb 2024 09:30
Actual End 28 Mar 2024 15:00
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
53.816541
-1.598817
Last Updated 28 Mar 2024 15:17
Works History for Activity GP00658575700 (Morris Lane, Kirkstall, Leeds)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Jan 2024
11:10
Permit Submitted
19 Feb 2024
09:30
15 Mar 2024
15:30
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Jan 2024
12:04
Permit Granted
19 Feb 2024
09:30
15 Mar 2024
15:30
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
2 Feb 2024
10:50
Permit Alteration Granted
19 Feb 2024
09:30
2 Apr 2024
16:30
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Feb 2024
09:43
Work Started
19 Feb 2024
09:30
2 Apr 2024
16:30
19 Feb 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
28 Mar 2024
15:17
Work Stopped
19 Feb 2024
09:30
2 Apr 2024
16:30
19 Feb 2024
09:30
28 Mar 2024
15:00
Completed

Works Permits for Morris Lane, Kirkstall, Leeds

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.