ROADWORK EVENT SUMMARY
Ramsgate Road, Sandwich between 6 Apr and 6 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Ramsgate Road, Sandwich

Kent County Council carried out Highway improvement works on Ramsgate Road, Sandwich.

These works were categorised as Major.

Multi-way signals were in place for some or all of the period.

The works were originally planned between 6 Apr 2024 and 30 Nov 2024 and were actually completed between 6 Apr 2024 (00:00) and 6 Nov 2024 (09:11). The works impacted the carriageway only.

The information for these works was last updated by Kent County Council on 6 November 2024 at 09:15.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Ramsgate Road, Sandwich

Works Details

WORKS COMPLETED
Major
Kent County Council logo
These works are handled by:
Kent County Council
Kent County Council logo
Local Authority:
Kent County Council
Works Reference GE50507_00146_CI2_2024
Permit Number 02
Place Name Ramsgate Road
Sandwich
Proposed Start 6 Apr 2024
Proposed End 30 Nov 2024
Actual Start 6 Apr 2024 00:00
Actual End 6 Nov 2024 09:11
Traffic Management Multi-way signals
Impact Carriageway
Coordinates
Lat, Lon
51.276268
1.342301
Last Updated 6 Nov 2024 09:15
Contact Details for Activity GE50507_00146_CI2_2024 (Ramsgate Road, Sandwich)

In the event that you have an issue with these works, please contact Kent County Council, the works operator.

It would assist the organisation if you quote the work reference number of GE50507_00146_CI2_2024.

Kent County Council
Telephone03000 418 181
Works History for Activity GE50507_00146_CI2_2024 (Ramsgate Road, Sandwich)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Mar 2024
09:16
Permit Submitted
6 Apr 2024
01:00
14 May 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Mar 2024
10:12
Permit Granted
6 Apr 2024
01:00
14 May 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
8 Apr 2024
08:08
Work Started
6 Apr 2024
01:00
14 May 2024
00:59
6 Apr 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
30 Apr 2024
16:11
Permit Alteration Granted
6 Apr 2024
01:00
4 Jun 2024
00:59
6 Apr 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Jun 2024
16:30
Permit Alteration Granted
6 Apr 2024
01:00
29 Jul 2024
00:59
6 Apr 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
26 Jul 2024
14:32
Permit Alteration Granted
6 Apr 2024
01:00
1 Oct 2024
00:59
6 Apr 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Aug 2024
10:13
Permit Alteration Granted
6 Apr 2024
01:00
30 Nov 2024
23:59
6 Apr 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
6 Nov 2024
09:15
Work Stopped
6 Apr 2024
01:00
30 Nov 2024
23:59
6 Apr 2024
01:00
6 Nov 2024
09:11
Completed

Works Permits for Ramsgate Road, Sandwich

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT03 (Activities ancillary to those permitted - supplementary information)

For the activities hereby permitted, it is a condition of this permit that, if there are changes to ancillary activities, either in the street to which the application relates or in an adjacent street that become known about within the duration of the permit, the authority must be notified.

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT08b (Manual control of traffic management)

For the activities hereby permitted, it is a condition of this permit that, for the traffic management deployed (state type), it is manually operated between (x hours and y hours).

+
NCT09b (Traffic management arrangements to be in place)

For the activities hereby permitted, it is a condition of this permit that the works comprised in [specified part A/B] of the activities hereby permitted shall be subject to and shall occur only when the following traffic management measures are in place [or as attached in schedule.].

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.