Works Description for Renfrew Road, Hounslow

London Borough Of Hounslow are proposing to carry out Highway improvement works on Renfrew Road, Hounslow.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 October 2024 and could run through until 25 October 2024. The works will impact the footway and carriageway.

The information for these works was last updated by London Borough Of Hounslow on 13 September 2024 at 16:30.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Renfrew Road, Hounslow

Works Details

WORKS PLANNED
Major
London Borough Of Hounslow logo
These works are handled by:
London Borough Of Hounslow
London Borough Of Hounslow logo
Local Authority:
London Borough Of Hounslow
Works Reference FQ00291313109
Permit Number 02
Place Name Renfrew Road
Hounslow
Proposed Start 14 Oct 2024
Proposed End 25 Oct 2024
Actual Start
Actual End
Traffic Management Road closure
Impact Footway, Carriageway
Coordinates
Lat, Lon
51.474818
-0.387545
Last Updated 13 Sep 2024 16:30
Works History for Activity FQ00291313109 (Renfrew Road, Hounslow)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
25 Jul 2024
14:14
Permit Submitted
27 Aug 2024
09:00
9 Sep 2024
17:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Aug 2024
15:44
Permit Granted
27 Aug 2024
09:00
9 Sep 2024
17:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
13 Sep 2024
17:30
Permit Alteration Granted
14 Oct 2024
10:30
25 Oct 2024
17:00
Planned

Works Permits for Renfrew Road, Hounslow

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT09a (Changes to traffic management arrangements)

For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.