ROADWORK EVENT SUMMARY
Clock Island, Bickenhill, Solihull between 18 Dec 2024 and 30 Sep 2025

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Clock Island, Bickenhill, Solihull

National Highways are proposing to carry out Highway improvement works on Clock Island, Bickenhill, Solihull.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 18 December 2024 and could run through until 30 September 2025. The works will impact the carriageway only.

The information for these works was last updated by National Highways on 15 November 2024 at 11:05.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Clock Island, Bickenhill, Solihull

Works Details

WORKS PLANNED
Major
National Highways logo
These works are handled by:
National Highways
Solihull Metropolitan Borough Council logo
Local Authority:
Solihull Metropolitan Borough Council
Works Reference FN40938512552
Permit Number 02
Place Name Clock Island
Bickenhill
Solihull
Proposed Start 18 Dec 2024
Proposed End 30 Sep 2025
Actual Start
Actual End
Traffic Management Multi-way signals
Impact Carriageway
Coordinates
Lat, Lon
52.44408
-1.72449
Last Updated 15 Nov 2024 11:05
Contact Details for Activity FN40938512552 (Clock Island, Bickenhill, Solihull)

In the event that you have an issue with these works, please contact National Highways, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Solihull Metropolitan Borough Council that authorised the works.

It would assist the organisations if you quote the work reference number of FN40938512552.

National Highways
Websitehttps://report.nationalhighways.co.uk/
Telephone0300 123 5000
Works History for Activity FN40938512552 (Clock Island, Bickenhill, Solihull)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Nov 2024
11:05
Permit Submitted
18 Dec 2024
00:01
1 Oct 2025
00:59
Planned

Works Permits for Clock Island, Bickenhill, Solihull

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.