ROADWORK EVENT SUMMARY
Abbey Street, Nottingham between 20 Aug 2024 and 5 Aug 2025

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Abbey Street, Nottingham

National Highways are carrying out Works for road purposes on Abbey Street, Nottingham.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 20 August 2024 at 20:00 and could run through until 5 August 2025. The works will impact the carriageway only.

The information for these works was last updated by National Highways on 12 December 2024 at 08:32.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Abbey Street, Nottingham

Works Details

WORKS IN PROGRESS
Major
National Highways logo
These works are handled by:
National Highways
Nottingham City Council logo
Local Authority:
Nottingham City Council
Works Reference FN40779311280
Permit Number 02
Place Name Abbey Street
Nottingham
Proposed Start 19 Aug 2024
Proposed End 5 Aug 2025
Actual Start 20 Aug 2024 20:00
Actual End
Traffic Management Lane closure
Impact Carriageway
Coordinates
Lat, Lon
52.941036
-1.18108
Last Updated 12 Dec 2024 08:32
Contact Details for Activity FN40779311280 (Abbey Street, Nottingham)

In the event that you have an issue with these works, please contact National Highways, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Nottingham City Council that authorised the works.

It would assist the organisations if you quote the work reference number of FN40779311280.

National Highways
Websitehttps://report.nationalhighways.co.uk/
Telephone0300 123 5000
Works History for Activity FN40779311280 (Abbey Street, Nottingham)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Mar 2024
13:38
Permit Submitted
19 Jun 2024
21:00
24 Jan 2025
06:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Apr 2024
08:41
Permit Granted
19 Jun 2024
21:00
24 Jan 2025
06:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Jun 2024
16:30
Permit Alteration Granted
29 Jul 2024
21:00
5 Jul 2025
07:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
6 Aug 2024
11:43
Permit Alteration Granted
19 Aug 2024
21:00
7 Jul 2025
07:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Aug 2024
10:49
Work Started
19 Aug 2024
21:00
7 Jul 2025
07:00
20 Aug 2024
21:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Dec 2024
08:32
Permit Alteration Granted
19 Aug 2024
21:00
5 Aug 2025
07:00
20 Aug 2024
21:00
In Progress

Works Permits for Abbey Street, Nottingham

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT09b (Traffic management arrangements to be in place)

For the activities hereby permitted, it is a condition of this permit that the works comprised in [specified part A/B] of the activities hereby permitted shall be subject to and shall occur only when the following traffic management measures are in place [or as attached in schedule.].

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.