ROADWORK EVENT SUMMARY
Cheltenham Road, Pitchcombe, Stroud between 29 Jul and 7 Oct 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Cheltenham Road, Pitchcombe, Stroud

Gloucestershire County Council carried out Highway repair and maintenance works on Cheltenham Road, Pitchcombe, Stroud.

These works were categorised as Major.

Two-way signals were in place for some or all of the period.

The works were originally planned between 29 Jul 2024 and 1 Nov 2024 and were actually completed between 29 Jul 2024 (08:30) and 7 Oct 2024 (15:30). The works impacted the carriageway and verge.

The information for these works was last updated by Gloucestershire County Council on 25 October 2024 at 11:14.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Cheltenham Road, Pitchcombe, Stroud

Works Details

WORKS COMPLETED
Major
Gloucestershire County Council logo
These works are handled by:
Gloucestershire County Council
Gloucestershire County Council logo
Local Authority:
Gloucestershire County Council
Works Reference EY102GH1902000028946
Permit Number 02
Place Name Cheltenham Road
Pitchcombe
Stroud
Proposed Start 29 Jul 2024
Proposed End 1 Nov 2024
Actual Start 29 Jul 2024 08:30
Actual End 7 Oct 2024 15:30
Traffic Management Two-way signals
Impact Carriageway, Verge
Coordinates
Lat, Lon
51.773611
-2.212596
Last Updated 25 Oct 2024 11:14
Works History for Activity EY102GH1902000028946 (Cheltenham Road, Pitchcombe, Stroud)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Jul 2024
11:34
Permit Submitted
29 Jul 2024
09:30
17 Aug 2024
00:58
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Jul 2024
11:35
Permit Alteration Granted
29 Jul 2024
09:30
17 Aug 2024
00:58
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Jul 2024
13:12
Permit Granted
29 Jul 2024
09:30
17 Aug 2024
00:58
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Aug 2024
10:46
Permit Alteration Granted
29 Jul 2024
09:30
24 Aug 2024
00:58
29 Jul 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Aug 2024
11:49
Permit Alteration Granted
29 Jul 2024
09:30
31 Aug 2024
00:58
29 Jul 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
30 Aug 2024
15:47
Traffic Management Updated
29 Jul 2024
09:30
31 Aug 2024
00:58
29 Jul 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
30 Aug 2024
16:03
Permit Alteration Granted
29 Jul 2024
09:30
31 Aug 2024
00:58
29 Jul 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Sep 2024
16:48
Permit Alteration Granted
29 Jul 2024
09:30
27 Sep 2024
00:58
29 Jul 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Sep 2024
15:48
Permit Alteration Granted
29 Jul 2024
09:30
24 Oct 2024
00:58
29 Jul 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Oct 2024
09:47
Work Stopped
29 Jul 2024
09:30
24 Oct 2024
00:58
29 Jul 2024
09:30
7 Oct 2024
09:46
Completed
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
25 Oct 2024
09:16
Work Stopped (Reverted)
29 Jul 2024
09:30
24 Oct 2024
00:58
29 Jul 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
25 Oct 2024
09:31
Work Stopped
29 Jul 2024
09:30
24 Oct 2024
00:58
29 Jul 2024
09:30
7 Oct 2024
16:30
Completed
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
25 Oct 2024
12:14
Permit Alteration Granted
29 Jul 2024
09:30
1 Nov 2024
23:58
29 Jul 2024
09:30
7 Oct 2024
16:30
Completed

Works Permits for Cheltenham Road, Pitchcombe, Stroud

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.