ROADWORK EVENT SUMMARY
Southend Road, Wickford between 28 and 29 Jan 2025

Works Description for Southend Road, Wickford

Essex County Council carried out Highway improvement works on Southend Road, Wickford.

Multi-way signals were in place for some or all of the period.

The works were originally planned between 28 Jan 2025 and 29 Jan 2025 and were actually completed between 28 Jan 2025 (20:00) and 29 Jan 2025 (05:00). The works impacted the carriageway only.

The information for these works was last updated by Essex County Council on 29 January 2025 at 10:39.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Southend Road, Wickford

Works Details

WORKS COMPLETED
Essex County Council logo
These works are handled by:
Essex County Council
Essex County Council logo
Local Authority:
Essex County Council
Works Reference EP201EH2379644
Permit Number 02
Place Name Southend Road
Wickford
Proposed Start 28 Jan 2025
Proposed End 29 Jan 2025
Actual Start 28 Jan 2025 20:00
Actual End 29 Jan 2025 05:00
Traffic Management Multi-way signals
Impact Carriageway
Coordinates
Lat, Lon
51.611304
0.537988
Last Updated 29 Jan 2025 10:39
Works History for Activity EP201EH2379644 (Southend Road, Wickford)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Jan 2025
08:32
Permit Submitted
27 Jan 2025
00:00
28 Jan 2025
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Jan 2025
10:02
Permit Granted
27 Jan 2025
00:00
28 Jan 2025
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Jan 2025
07:53
Permit Alteration Granted
28 Jan 2025
00:00
29 Jan 2025
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
29 Jan 2025
10:39
Work Started
28 Jan 2025
00:00
29 Jan 2025
23:59
28 Jan 2025
20:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
29 Jan 2025
10:39
Work Stopped
28 Jan 2025
00:00
29 Jan 2025
23:59
28 Jan 2025
20:00
29 Jan 2025
05:00
Completed

Works Permits for Southend Road, Wickford

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT12a (- Limit timing of certain activities)

For the activities hereby permitted, it is a condition of this permit the following working methodology [insert methodology] shall only take place between [start time] and [end time] on weekdays and/or [start time] and [end time] on Saturdays and/or [start time] and [end time] on Sundays or Bank Holidays and must not continue beyond these times.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.