ROADWORK EVENT SUMMARY
Coppermill Lane, Walthamstow between 12 and 15 Dec 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Coppermill Lane, Walthamstow

UK Power Networks Eastern & London carried out Utility repair and maintenance works on Coppermill Lane, Walthamstow.

These works were categorised as Urgent Works with an immediate start.

The works did not impact the carriageway.

The works were originally planned between 12 Dec 2024 and 18 Dec 2024 and were actually completed between 12 Dec 2024 (09:53) and 15 Dec 2024 (18:50). The works impacted the footway only.

The information for these works was last updated by UK Power Networks Eastern & London on 16 December 2024 at 08:30.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Coppermill Lane, Walthamstow

Works Details

WORKS COMPLETED
Immediate - urgent
UK Power Networks Eastern & London logo
These works are handled by:
UK Power Networks Eastern & London
London Borough Of Waltham Forest logo
Local Authority:
London Borough Of Waltham Forest
Works Reference EC40086419774
Permit Number 01
Place Name Coppermill Lane
Walthamstow
Proposed Start 12 Dec 2024
Proposed End 18 Dec 2024
Actual Start 12 Dec 2024 09:53
Actual End 15 Dec 2024 18:50
Traffic Management No carriageway incursion
Impact Footway
Coordinates
Lat, Lon
51.580488
-0.039782
Last Updated 16 Dec 2024 08:30
Works History for Activity EC40086419774 (Coppermill Lane, Walthamstow)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Dec 2024
09:56
Work Started
12 Dec 2024
09:53
18 Dec 2024
09:53
12 Dec 2024
09:53
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Dec 2024
08:30
Work Stopped
12 Dec 2024
09:53
18 Dec 2024
09:53
12 Dec 2024
09:53
15 Dec 2024
18:50
Completed

Works Permits for Coppermill Lane, Walthamstow

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.