ROADWORK EVENT SUMMARY
St John's Wood Park, Swiss Cottage, London between 6 Jan and 7 Feb 2025

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for St John's Wood Park, Swiss Cottage, London

UK Power Networks Eastern & London are proposing to carry out Statutory Infrastructure Works on St John's Wood Park, Swiss Cottage, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 7 February 2025. The works will impact the carriageway only.

The information for these works was last updated by UK Power Networks Eastern & London on 19 December 2024 at 15:21.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for St John's Wood Park, Swiss Cottage, London

Works Details

WORKS PLANNED
Major
UK Power Networks Eastern & London logo
These works are handled by:
UK Power Networks Eastern & London
London Borough Of Camden logo
Local Authority:
London Borough Of Camden
Works Reference EC40067450489
Permit Number 04
Place Name St John's Wood Park
Swiss Cottage
London
Proposed Start 6 Jan 2025
Proposed End 7 Feb 2025
Actual Start
Actual End
Traffic Management Multi-way signals
Impact Carriageway
Coordinates
Lat, Lon
51.539923
-0.173843
Last Updated 19 Dec 2024 15:21
Works History for Activity EC40067450489 (St John's Wood Park, Swiss Cottage, London)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Dec 2024
10:21
Permit Submitted
6 Jan 2025
08:00
7 Feb 2025
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Dec 2024
13:55
Permit Alteration Granted
6 Jan 2025
08:00
7 Feb 2025
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Dec 2024
15:21
Permit Granted
6 Jan 2025
08:00
7 Feb 2025
18:00
Planned

Works Permits for St John's Wood Park, Swiss Cottage, London

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT03 (Activities ancillary to those permitted - supplementary information)

For the activities hereby permitted, it is a condition of this permit that, if there are changes to ancillary activities, either in the street to which the application relates or in an adjacent street that become known about within the duration of the permit, the authority must be notified.

+
NCT09b (Traffic management arrangements to be in place)

For the activities hereby permitted, it is a condition of this permit that the works comprised in [specified part A/B] of the activities hereby permitted shall be subject to and shall occur only when the following traffic management measures are in place [or as attached in schedule.].

+
NCT09c (Signal removal from operation when no longer required)

This condition is attached to permits in cases where temporary traffic signals are used. For the activities hereby permitted, it is a condition of this permit that activities using portable traffic signals must have the signals (whether manually operated or not) removed from use as soon as possible and no later than four hours after completion of works irrespective of day of completion.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.