ROADWORK EVENT SUMMARY
Paddock Way, Sawston between 11 Nov and 2 Dec 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Paddock Way, Sawston

UK Power Networks Eastern & London carried out Utility asset works on Paddock Way, Sawston.

These works were categorised as Major.

Multi-way signals were in place for some or all of the period.

The works were originally planned between 11 Nov 2024 and 29 Nov 2024 and were actually completed between 11 Nov 2024 (15:50) and 2 Dec 2024 (14:17). The works impacted the footway, carriageway and verge.

The information for these works was last updated by UK Power Networks Eastern & London on 2 December 2024 at 14:17.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Paddock Way, Sawston

Works Details

WORKS COMPLETED
Major
UK Power Networks Eastern & London logo
These works are handled by:
UK Power Networks Eastern & London
Cambridgeshire County Council logo
Local Authority:
Cambridgeshire County Council
Works Reference EC30072878036
Permit Number 01
Place Name Paddock Way
Sawston
Proposed Start 11 Nov 2024
Proposed End 29 Nov 2024
Actual Start 11 Nov 2024 15:50
Actual End 2 Dec 2024 14:17
Traffic Management Multi-way signals
Impact Footway, Carriageway, Verge
Coordinates
Lat, Lon
52.12177
0.172019
Last Updated 2 Dec 2024 14:17
Works History for Activity EC30072878036 (Paddock Way, Sawston)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Oct 2024
08:37
Permit Submitted
18 Nov 2024
08:00
1 Dec 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
8 Oct 2024
16:37
Permit Alteration Granted
25 Nov 2024
08:00
8 Dec 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Oct 2024
12:25
Permit Granted
25 Nov 2024
08:00
8 Dec 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Oct 2024
16:19
Permit Alteration Granted
25 Nov 2024
08:00
8 Dec 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Nov 2024
10:21
Permit Alteration Granted
11 Nov 2024
08:00
24 Nov 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Nov 2024
15:53
Work Started
11 Nov 2024
08:00
24 Nov 2024
18:00
11 Nov 2024
15:50
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Nov 2024
11:23
Permit Alteration Granted
11 Nov 2024
08:00
29 Nov 2024
18:00
11 Nov 2024
15:50
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
28 Nov 2024
15:38
Traffic Management Updated
11 Nov 2024
08:00
29 Nov 2024
18:00
11 Nov 2024
15:50
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
29 Nov 2024
14:13
Traffic Management Updated
11 Nov 2024
08:00
29 Nov 2024
18:00
11 Nov 2024
15:50
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
29 Nov 2024
14:17
Traffic Management Updated
11 Nov 2024
08:00
29 Nov 2024
18:00
11 Nov 2024
15:50
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
2 Dec 2024
14:17
Work Stopped
11 Nov 2024
08:00
29 Nov 2024
18:00
11 Nov 2024
15:50
2 Dec 2024
14:17
Completed

Works Permits for Paddock Way, Sawston

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT03 (Activities ancillary to those permitted - supplementary information)

For the activities hereby permitted, it is a condition of this permit that, if there are changes to ancillary activities, either in the street to which the application relates or in an adjacent street that become known about within the duration of the permit, the authority must be notified.

+
NCT09b (Traffic management arrangements to be in place)

For the activities hereby permitted, it is a condition of this permit that the works comprised in [specified part A/B] of the activities hereby permitted shall be subject to and shall occur only when the following traffic management measures are in place [or as attached in schedule.].

+
NCT09c (Signal removal from operation when no longer required)

This condition is attached to permits in cases where temporary traffic signals are used. For the activities hereby permitted, it is a condition of this permit that activities using portable traffic signals must have the signals (whether manually operated or not) removed from use as soon as possible and no later than four hours after completion of works irrespective of day of completion.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.