ROADWORK EVENT SUMMARY
Charlotte Road, Wallington between 17 and 23 Feb 2025
Works Description for Charlotte Road, Wallington
Ses Water (formerly Sutton & East Surrey Water Company) were proposing to carry out roadworks on Charlotte Road, Wallington.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 17 February 2025 and run through until 23 February 2025. The works were due to impact the carriageway only.
The information for these works was last updated by Ses Water (formerly Sutton & East Surrey Water Company) on 29 October 2024 at 08:09.
Works Map for Charlotte Road, Wallington
Works Details
Ses Water (formerly Sutton & East Surrey Water Company)
London Borough Of Sutton
Works Reference | DZ001J0GG6YB |
Permit Number | 01 |
Place Name |
Charlotte Road Wallington |
Proposed Start | 17 Feb 2025 |
Proposed End | 23 Feb 2025 |
Actual Start | |
Actual End |
Traffic Management | Road closure |
Impact | Carriageway |
Coordinates Lat, Lon |
51.358431 -0.144585 |
Last Updated | 29 Oct 2024 08:09 |
In the event that you have an issue with these works, please contact Ses Water (formerly Sutton & East Surrey Water Company), the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.
Should the issue remain, you may also contact the local authority, London Borough Of Sutton that authorised the works.
It would assist the organisations if you quote the work reference number of DZ001J0GG6YB.
Telephone | 01737 772000 |
Works Permits for Charlotte Road, Wallington
For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.
Applies to all permits.
For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.
Applies to all permits.
For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.
Applies to all permits.
Proposed Work Dates
Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.
Problems with roadworks?
On rare occasions, issues may occur during or after the completion of roadworks, such as:
- Poor reinstatement of the footpath or the carriageway.
- Rubbish and mess remaining after the works have completed.
- Traffic management issues during the works.
- Equipment left behind after the works have completed.
- Any other issues or disruption that the works may be causing.
In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.
In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.
Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.
Contains public sector information licensed under the Open Government Licence v3.0.