ROADWORK EVENT SUMMARY
Hatfield Lane, Edenthorpe, Doncaster between 21 Oct and 25 Nov 2024

Works Description for Hatfield Lane, Edenthorpe, Doncaster

Doncaster Metropolitan Borough Council are carrying out Highway repair and maintenance works on Hatfield Lane, Edenthorpe, Doncaster.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 21 October 2024 at 08:00 and could run through until 25 November 2024. The works will impact the carriageway only.

The information for these works was last updated by Doncaster Metropolitan Borough Council on 21 October 2024 at 11:39.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Hatfield Lane, Edenthorpe, Doncaster

Works Details

WORKS IN PROGRESS
Major
These works are handled by:
Doncaster Metropolitan Borough Council
Local Authority:
Doncaster Metropolitan Borough Council
Works Reference DQ02027951-03
Permit Number 02
Place Name Hatfield Lane
Edenthorpe
Doncaster
Proposed Start 21 Oct 2024
Proposed End 25 Nov 2024
Actual Start 21 Oct 2024 08:00
Actual End
Traffic Management Multi-way signals
Impact Carriageway
Coordinates
Lat, Lon
53.547671
-1.049257
Last Updated 21 Oct 2024 11:39
Works History for Activity DQ02027951-03 (Hatfield Lane, Edenthorpe, Doncaster)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Oct 2024
16:02
Permit Submitted
21 Oct 2024
01:00
25 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Oct 2024
10:20
Work Started
21 Oct 2024
01:00
25 Nov 2024
00:00
21 Oct 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Oct 2024
10:27
Permit Alteration Granted
21 Oct 2024
01:00
25 Nov 2024
00:00
21 Oct 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Oct 2024
12:39
Permit Granted
21 Oct 2024
01:00
25 Nov 2024
00:00
21 Oct 2024
09:00
In Progress

Works Permits for Hatfield Lane, Edenthorpe, Doncaster

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT08b (Manual control of traffic management)

For the activities hereby permitted, it is a condition of this permit that, for the traffic management deployed (state type), it is manually operated between (x hours and y hours).

+
NCT09a (Changes to traffic management arrangements)

For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority before these changes are made.

+
NCT09c (Signal removal from operation when no longer required)

This condition is attached to permits in cases where temporary traffic signals are used. For the activities hereby permitted, it is a condition of this permit that activities using portable traffic signals must have the signals (whether manually operated or not) removed from use as soon as possible and no later than four hours after completion of works irrespective of day of completion.

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.