ROADWORK EVENT SUMMARY
Carrington Street, West End, London between 28 Aug and 20 Dec 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Carrington Street, West End, London

City Of Westminster carried out Highway repair and maintenance works on Carrington Street, West End, London.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 28 Aug 2024 and 20 Dec 2024 and were actually completed between 28 Aug 2024 (08:00) and 20 Dec 2024 (17:00). The works impacted the carriageway only.

The information for these works was last updated by City Of Westminster on 20 December 2024 at 17:09.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Carrington Street, West End, London

Works Details

WORKS COMPLETED
Major
City Of Westminster logo
These works are handled by:
City Of Westminster
City Of Westminster logo
Local Authority:
City Of Westminster
Works Reference CT02261764718
Permit Number 03
Place Name Carrington Street
West End
London
Proposed Start 28 Aug 2024
Proposed End 20 Dec 2024
Actual Start 28 Aug 2024 08:00
Actual End 20 Dec 2024 17:00
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
51.506176
-0.147008
Last Updated 20 Dec 2024 17:09
Works History for Activity CT02261764718 (Carrington Street, West End, London)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Aug 2024
17:37
Permit Submitted
28 Aug 2024
09:00
25 Oct 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
28 Aug 2024
08:10
Permit Granted
28 Aug 2024
09:00
25 Oct 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
28 Aug 2024
10:48
Work Started
28 Aug 2024
09:00
25 Oct 2024
18:00
28 Aug 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Oct 2024
10:43
Permit Alteration Granted
28 Aug 2024
09:00
28 Nov 2024
17:00
28 Aug 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Nov 2024
15:31
Permit Alteration Granted
28 Aug 2024
09:00
13 Dec 2024
17:00
28 Aug 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Dec 2024
15:22
Permit Alteration Granted
28 Aug 2024
09:00
20 Dec 2024
17:00
28 Aug 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Dec 2024
17:09
Work Stopped
28 Aug 2024
09:00
20 Dec 2024
17:00
28 Aug 2024
09:00
20 Dec 2024
17:00
Completed

Works Permits for Carrington Street, West End, London

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.