ROADWORK EVENT SUMMARY
London Wall, London between 1 Jul and 18 Dec 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for London Wall, London

City Of London Corporation carried out Highway repair and maintenance works on London Wall, London.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 1 Jul 2024 and 18 Dec 2024 and were actually completed between 1 Jul 2024 (08:00) and 18 Dec 2024 (17:00). The works impacted the carriageway only.

The information for these works was last updated by City Of London Corporation on 19 December 2024 at 06:44.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for London Wall, London

Works Details

WORKS COMPLETED
Major
City Of London Corporation logo
These works are handled by:
City Of London Corporation
City Of London Corporation logo
Local Authority:
City Of London Corporation
Works Reference CR01094625357
Permit Number 02
Place Name London Wall
London
Proposed Start 1 Jul 2024
Proposed End 18 Dec 2024
Actual Start 1 Jul 2024 08:00
Actual End 18 Dec 2024 17:00
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
51.51754
-0.09378
Last Updated 19 Dec 2024 06:44
Works History for Activity CR01094625357 (London Wall, London)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Jun 2024
14:23
Permit Submitted
1 Jul 2024
09:00
27 Sep 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Jun 2024
13:00
Permit Granted
1 Jul 2024
09:00
27 Sep 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Jul 2024
08:02
Work Started
1 Jul 2024
09:00
27 Sep 2024
18:00
1 Jul 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
26 Sep 2024
11:07
Permit Alteration Granted
1 Jul 2024
09:00
24 Oct 2024
18:00
1 Jul 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Oct 2024
11:58
Permit Alteration Granted
1 Jul 2024
09:00
15 Nov 2024
17:00
1 Jul 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Nov 2024
13:25
Permit Alteration Granted
1 Jul 2024
09:00
28 Nov 2024
17:00
1 Jul 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
29 Nov 2024
10:48
Permit Alteration Granted
1 Jul 2024
09:00
13 Dec 2024
17:00
1 Jul 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Dec 2024
14:50
Permit Alteration Granted
1 Jul 2024
09:00
18 Dec 2024
17:00
1 Jul 2024
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Dec 2024
06:44
Work Stopped
1 Jul 2024
09:00
18 Dec 2024
17:00
1 Jul 2024
09:00
18 Dec 2024
17:00
Completed

Works Permits for London Wall, London

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.