ROADWORK EVENT SUMMARY
Arbury Road, Cambridge between 27 Jun 2022 and 1 Dec 2024

Works Description for Arbury Road, Cambridge

Cambridgeshire County Council are carrying out Highway improvement works on Arbury Road, Cambridge.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 27 June 2022 at 08:00 and could run through until 1 December 2024. The works will impact the footway and carriageway.

The information for these works was last updated by Cambridgeshire County Council on 12 August 2024 at 13:44.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Arbury Road, Cambridge

Works Details

WORKS IN PROGRESS
Major
Cambridgeshire County Council logo
These works are handled by:
Cambridgeshire County Council
Cambridgeshire County Council logo
Local Authority:
Cambridgeshire County Council
Works Reference CL900SCHEMES-MIL-12
Permit Number 02
Place Name Arbury Road
Cambridge
Proposed Start 27 Jun 2022
Proposed End 1 Dec 2024
Actual Start 27 Jun 2022 08:00
Actual End
Traffic Management Multi-way signals
Impact Footway, Carriageway
Coordinates
Lat, Lon
52.220849
0.13419
Last Updated 12 Aug 2024 13:44
Works History for Activity CL900SCHEMES-MIL-12 (Arbury Road, Cambridge)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 May 2022
14:29
Permit Submitted
27 Jun 2022
23:00
29 Apr 2024
23:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
29 Jun 2022
09:25
Permit Alteration Granted
27 Jun 2022
23:00
29 Apr 2024
23:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
29 Jun 2022
09:39
Permit Granted
27 Jun 2022
23:00
29 Apr 2024
23:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
29 Jun 2022
10:38
Work Started
27 Jun 2022
23:00
29 Apr 2024
23:00
27 Jun 2022
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
25 Jul 2022
13:00
Permit Alteration Granted
27 Jun 2022
23:00
29 Apr 2024
23:00
27 Jun 2022
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Nov 2022
12:23
Permit Alteration Granted
27 Jun 2022
23:00
29 Apr 2024
23:00
27 Jun 2022
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
6 Jun 2023
11:56
Permit Alteration Granted
27 Jun 2022
23:00
1 Dec 2024
23:00
27 Jun 2022
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Aug 2024
14:40
Traffic Management Updated
28 Jun 2022
00:00
1 Dec 2024
23:00
27 Jun 2022
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Aug 2024
14:44
Traffic Management Updated
28 Jun 2022
00:00
1 Dec 2024
23:00
27 Jun 2022
09:00
In Progress

Works Permits for Arbury Road, Cambridge

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT09a (Changes to traffic management arrangements)

For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority before these changes are made.

+
NCT09c (Signal removal from operation when no longer required)

This condition is attached to permits in cases where temporary traffic signals are used. For the activities hereby permitted, it is a condition of this permit that activities using portable traffic signals must have the signals (whether manually operated or not) removed from use as soon as possible and no later than four hours after completion of works irrespective of day of completion.

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.