ROADWORK EVENT SUMMARY
Bridgemont, Bridgemont, Whaley Bridge between 12 and 14 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Bridgemont, Bridgemont, Whaley Bridge

BT are carrying out Utility asset works on Bridgemont, Bridgemont, Whaley Bridge.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 12 November 2024 at 19:00 and could run through until 14 November 2024. The works will impact the footway and carriageway.

The information for these works was last updated by BT on 13 November 2024 at 08:44.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Bridgemont, Bridgemont, Whaley Bridge

Works Details

WORKS IN PROGRESS
BT logo
These works are handled by:
BT
Derbyshire County Council logo
Local Authority:
Derbyshire County Council
Works Reference BC43992051184
Permit Number 02
Place Name Bridgemont
Bridgemont
Whaley Bridge
Proposed Start 12 Nov 2024
Proposed End 14 Nov 2024
Actual Start 12 Nov 2024 19:00
Actual End
Traffic Management Two-way signals
Impact Footway, Carriageway
Coordinates
Lat, Lon
53.336051
-1.983047
Last Updated 13 Nov 2024 08:44
Contact Details for Activity BC43992051184 (Bridgemont, Bridgemont, Whaley Bridge)

In the event that you have an issue with these works, please contact BT, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Derbyshire County Council that authorised the works.

It would assist the organisations if you quote the work reference number of BC43992051184.

BT
Telephone03301 233 753
Works History for Activity BC43992051184 (Bridgemont, Bridgemont, Whaley Bridge)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Nov 2024
15:59
Permit Submitted
12 Nov 2024
19:00
14 Nov 2024
04:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Nov 2024
16:36
Permit Granted
12 Nov 2024
19:00
14 Nov 2024
04:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
13 Nov 2024
08:44
Work Started
12 Nov 2024
19:00
14 Nov 2024
04:00
12 Nov 2024
19:00
In Progress

Works Permits for Bridgemont, Bridgemont, Whaley Bridge

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT09a (Changes to traffic management arrangements)

For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority before these changes are made.

+
NCT09c (Signal removal from operation when no longer required)

This condition is attached to permits in cases where temporary traffic signals are used. For the activities hereby permitted, it is a condition of this permit that activities using portable traffic signals must have the signals (whether manually operated or not) removed from use as soon as possible and no later than four hours after completion of works irrespective of day of completion.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT12a (- Limit timing of certain activities)

For the activities hereby permitted, it is a condition of this permit the following working methodology [insert methodology] shall only take place between [start time] and [end time] on weekdays and/or [start time] and [end time] on Saturdays and/or [start time] and [end time] on Sundays or Bank Holidays and must not continue beyond these times.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.