ROADWORK EVENT SUMMARY
Douglas Terrace East Back, Concord, Washington on 21 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Douglas Terrace East Back, Concord, Washington

BT were proposing to carry out Utility asset works on Douglas Terrace East Back, Concord, Washington.

There were no traffic signals or road closures necessary for these works and traffic would have operated on a give-and-take basis. However, the works were cancelled.

The works were scheduled for 21 November 2024 The works were due to impact the footway only.

The information for these works was last updated by BT on 19 November 2024 at 11:22.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Douglas Terrace East Back, Concord, Washington

Works Details

WORKS CANCELLED
BT logo
These works are handled by:
BT
Local Authority:
Sunderland City Council
Works Reference BC320NEWFTRND2D
Permit Number 02
Place Name Douglas Terrace East Back
Concord
Washington
Proposed Start 21 Nov 2024
Proposed End 21 Nov 2024
Actual Start
Actual End
Traffic Management Give and take
Impact Footway
Coordinates
Lat, Lon
54.919304
-1.524249
Last Updated 19 Nov 2024 11:22
Contact Details for Activity BC320NEWFTRND2D (Douglas Terrace East Back, Concord, Washington)

In the event that you have an issue with these works, please contact BT, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Sunderland City Council that authorised the works.

It would assist the organisations if you quote the work reference number of BC320NEWFTRND2D.

BT
Telephone03301 233 753
Works History for Activity BC320NEWFTRND2D (Douglas Terrace East Back, Concord, Washington)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Nov 2024
09:19
Permit Submitted
21 Nov 2024
00:00
25 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Nov 2024
09:37
Permit Alteration Granted
21 Nov 2024
00:00
21 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Nov 2024
10:15
Permit Refused
21 Nov 2024
00:00
21 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Nov 2024
11:22
Permit Cancelled
21 Nov 2024
00:00
21 Nov 2024
00:00
Cancelled

Works Permits for Douglas Terrace East Back, Concord, Washington

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.