ROADWORK EVENT SUMMARY
Footpath Between Earning Street And Merton Walk, Cambridgeshire, Godmanchester between 18 and 20 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Footpath Between Earning Street And Merton Walk, Cambridgeshire, Godmanchester

BT were proposing to carry out Utility asset works on Footpath Between Earning Street And Merton Walk, Cambridgeshire, Godmanchester.

The works were originally planned to start 18 November 2024 and run through until 20 November 2024. The works were due to impact the footpath only.

The information for these works was last updated by BT on 12 November 2024 at 11:14.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Footpath Between Earning Street And Merton Walk, Cambridgeshire, Godmanchester

Works Details

PERMIT REFUSED
BT logo
These works are handled by:
BT
Cambridgeshire County Council logo
Local Authority:
Cambridgeshire County Council
Works Reference BC311002RBWFGNRP9M
Permit Number 03
Place Name Footpath Between Earning Street And Merton Walk
Cambridgeshire
Godmanchester
Proposed Start 18 Nov 2024
Proposed End 20 Nov 2024
Actual Start
Actual End
Traffic Management Some carriageway incursion
Impact Footpath
Coordinates
Lat, Lon
52.316721
-0.168493
Last Updated 12 Nov 2024 11:14
Contact Details for Activity BC311002RBWFGNRP9M (Footpath Between Earning Street And Merton Walk, Cambridgeshire, Godmanchester)

In the event that you have an issue with these works, please contact BT, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Cambridgeshire County Council that authorised the works.

It would assist the organisations if you quote the work reference number of BC311002RBWFGNRP9M.

BT
Telephone03301 233 753
Works History for Activity BC311002RBWFGNRP9M (Footpath Between Earning Street And Merton Walk, Cambridgeshire, Godmanchester)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Nov 2024
13:09
Permit Submitted
11 Nov 2024
00:00
13 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Nov 2024
10:06
Permit Alteration Granted
18 Nov 2024
00:00
20 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Nov 2024
11:14
Permit Refused
18 Nov 2024
00:00
20 Nov 2024
00:00
Planned

Works Permits for Footpath Between Earning Street And Merton Walk, Cambridgeshire, Godmanchester

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT03 (Activities ancillary to those permitted - supplementary information)

For the activities hereby permitted, it is a condition of this permit that, if there are changes to ancillary activities, either in the street to which the application relates or in an adjacent street that become known about within the duration of the permit, the authority must be notified.

+
NCT04a (Removal of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that all remaining excavated or stored backfill materials and/or any unemployed plant must be removed from the public highway within (x hours e.g. 24) or by the stipulated time (e.g. at the end of the working day or prior to the site being un-occupied) due to (stipulate reason for application of condition).

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.