ROADWORK EVENT SUMMARY
Chapel Street, Tameside, Dukinfield between 15 and 20 Nov 2024

Works Description for Chapel Street, Tameside, Dukinfield

BT carried out Utility asset works on Chapel Street, Tameside, Dukinfield.

Multi-way signals were in place for some or all of the period.

The works were originally planned between 14 Nov 2024 and 21 Nov 2024 and were actually completed between 15 Nov 2024 (10:18) and 20 Nov 2024 (10:30). The works impacted the footway and carriageway.

The information for these works was last updated by BT on 20 November 2024 at 10:49.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Chapel Street, Tameside, Dukinfield

Works Details

WORKS COMPLETED
BT logo
These works are handled by:
BT
Tameside Metropolitan Borough Council logo
Local Authority:
Tameside Metropolitan Borough Council
Works Reference BC311001WFSGJK0B
Permit Number 01
Place Name Chapel Street
Tameside
Dukinfield
Proposed Start 14 Nov 2024
Proposed End 21 Nov 2024
Actual Start 15 Nov 2024 10:18
Actual End 20 Nov 2024 10:30
Traffic Management Multi-way signals
Impact Footway, Carriageway
Coordinates
Lat, Lon
53.477376
-2.092669
Last Updated 20 Nov 2024 10:49
Contact Details for Activity BC311001WFSGJK0B (Chapel Street, Tameside, Dukinfield)

In the event that you have an issue with these works, please contact BT, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Tameside Metropolitan Borough Council that authorised the works.

It would assist the organisations if you quote the work reference number of BC311001WFSGJK0B.

BT
Telephone03301 233 753
Works History for Activity BC311001WFSGJK0B (Chapel Street, Tameside, Dukinfield)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Oct 2024
10:19
Permit Submitted
15 Nov 2024
00:00
22 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Oct 2024
14:50
Permit Granted
15 Nov 2024
00:00
22 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Nov 2024
16:30
Permit Alteration Granted
14 Nov 2024
00:00
21 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Nov 2024
11:51
Work Started
14 Nov 2024
00:00
21 Nov 2024
00:00
15 Nov 2024
10:18
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Nov 2024
10:49
Work Stopped
14 Nov 2024
00:00
21 Nov 2024
00:00
15 Nov 2024
10:18
20 Nov 2024
10:30
Completed

Works Permits for Chapel Street, Tameside, Dukinfield

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT09c (Signal removal from operation when no longer required)

This condition is attached to permits in cases where temporary traffic signals are used. For the activities hereby permitted, it is a condition of this permit that activities using portable traffic signals must have the signals (whether manually operated or not) removed from use as soon as possible and no later than four hours after completion of works irrespective of day of completion.

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.