ROADWORK EVENT SUMMARY
A5 From M69 J1 Roundabout To J B578, Hinckley And Bosworth between 13 and 24 Jan 2025

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for A5 From M69 J1 Roundabout To J B578, Hinckley And Bosworth

This is a PAA (Provisional Advance Authorisation) permit that has been granted before final details of an activity have been finalised. A full permit will be required before activities can commence.


BT were proposing to carry out Utility asset works on A5 From M69 J1 Roundabout To J B578, Hinckley And Bosworth.

These works were categorised as Major.

A lane was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 13 January 2025 and run through until 24 January 2025. The works were due to impact the footway and carriageway.

The information for these works was last updated by BT on 15 October 2024 at 13:39.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for A5 From M69 J1 Roundabout To J B578, Hinckley And Bosworth

Works Details

WORKS CANCELLED
Major (PAA)
BT logo
These works are handled by:
BT
National Highways logo
Local Authority:
National Highways
Works Reference BC008WF0KN26J
Permit Number 07
Place Name A5 From M69 J1 Roundabout To J B578
Hinckley And Bosworth
Proposed Start 13 Jan 2025
Proposed End 24 Jan 2025
Actual Start
Actual End
Traffic Management Lane closure
Impact Footway, Carriageway
Coordinates
Lat, Lon
52.513916
-1.35849
Last Updated 15 Oct 2024 13:39
Contact Details for Activity BC008WF0KN26J (A5 From M69 J1 Roundabout To J B578, Hinckley And Bosworth)

In the event that you have an issue with these works, please contact BT, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, National Highways that authorised the works.

It would assist the organisations if you quote the work reference number of BC008WF0KN26J.

BT
Telephone03301 233 753
National Highways
Websitehttps://report.nationalhighways.co.uk/
Telephone0300 123 5000
Works History for Activity BC008WF0KN26J (A5 From M69 J1 Roundabout To J B578, Hinckley And Bosworth)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
10 Oct 2024
16:14
Permit Submitted
13 Jan 2025
20:00
24 Jan 2025
06:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Oct 2024
16:22
Permit Refused
13 Jan 2025
20:00
24 Jan 2025
06:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Oct 2024
14:39
Permit Cancelled
13 Jan 2025
20:00
24 Jan 2025
06:00
Cancelled

Works Permits for A5 From M69 J1 Roundabout To J B578, Hinckley And Bosworth

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

+
NCT12a (- Limit timing of certain activities)

For the activities hereby permitted, it is a condition of this permit the following working methodology [insert methodology] shall only take place between [start time] and [end time] on weekdays and/or [start time] and [end time] on Saturdays and/or [start time] and [end time] on Sundays or Bank Holidays and must not continue beyond these times.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.