ROADWORK EVENT SUMMARY
Walton Road, Culcheth And Glazebury, Warrington between 11 and 21 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Walton Road, Culcheth And Glazebury, Warrington

Cadent Gas carried out Utility asset works on Walton Road, Culcheth And Glazebury, Warrington.

These works were categorised as Major.

Multi-way signals were in place for some or all of the period.

The works were originally planned between 11 Nov 2024 and 27 Nov 2024 and were actually completed between 11 Nov 2024 (08:00) and 21 Nov 2024 (17:05). The works impacted the footway and carriageway.

The information for these works was last updated by Cadent Gas on 22 November 2024 at 08:08.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Walton Road, Culcheth And Glazebury, Warrington

Works Details

WORKS COMPLETED
Major
Cadent Gas logo
These works are handled by:
Cadent Gas
Warrington Borough Council logo
Local Authority:
Warrington Borough Council
Works Reference AZ5031001362764
Permit Number 02
Place Name Walton Road
Culcheth And Glazebury
Warrington
Proposed Start 11 Nov 2024
Proposed End 27 Nov 2024
Actual Start 11 Nov 2024 08:00
Actual End 21 Nov 2024 17:05
Traffic Management Multi-way signals
Impact Footway, Carriageway
Coordinates
Lat, Lon
53.45103
-2.512415
Last Updated 22 Nov 2024 08:08
Contact Details for Activity AZ5031001362764 (Walton Road, Culcheth And Glazebury, Warrington)

In the event that you have an issue with these works, please contact Cadent Gas, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Warrington Borough Council that authorised the works.

It would assist the organisations if you quote the work reference number of AZ5031001362764.

Cadent Gas
Websitehttps://cadentgas.com/contact-us/contact-form
Telephone0800 111 999
Works History for Activity AZ5031001362764 (Walton Road, Culcheth And Glazebury, Warrington)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Nov 2024
00:10
Permit Submitted
18 Nov 2024
00:00
4 Dec 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Nov 2024
13:40
Permit Granted
18 Nov 2024
00:00
4 Dec 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Nov 2024
15:40
Permit Alteration Granted
11 Nov 2024
00:00
27 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Nov 2024
08:05
Work Started
11 Nov 2024
00:00
27 Nov 2024
00:00
11 Nov 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Nov 2024
08:08
Work Stopped
11 Nov 2024
00:00
27 Nov 2024
00:00
11 Nov 2024
08:00
21 Nov 2024
17:05
Completed

Works Permits for Walton Road, Culcheth And Glazebury, Warrington

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.