ROADWORK EVENT SUMMARY
Stonebridge Lane, Fulbourn between 17 and 27 Sep 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Stonebridge Lane, Fulbourn

Anglian Water carried out Utility repair and maintenance works on Stonebridge Lane, Fulbourn.

These works were categorised as Urgent Works with an immediate start.

The road was closed for some or all of the period.

The works were originally planned between 17 Sep 2024 and 27 Sep 2024 and were actually completed between 17 Sep 2024 (09:20) and 27 Sep 2024 (16:09). The works impacted the carriageway only.

The information for these works was last updated by Anglian Water on 27 September 2024 at 16:09.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Stonebridge Lane, Fulbourn

Works Details

WORKS COMPLETED
Immediate - urgent
Anglian Water logo
These works are handled by:
Anglian Water
Cambridgeshire County Council logo
Local Authority:
Cambridgeshire County Council
Works Reference AD03364664770
Permit Number 01
Place Name Stonebridge Lane
Fulbourn
Proposed Start 17 Sep 2024
Proposed End 27 Sep 2024
Actual Start 17 Sep 2024 09:20
Actual End 27 Sep 2024 16:09
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
52.178946
0.22901
Last Updated 27 Sep 2024 16:09
Works History for Activity AD03364664770 (Stonebridge Lane, Fulbourn)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Sep 2024
10:29
Work Started
17 Sep 2024
10:20
23 Sep 2024
01:00
17 Sep 2024
10:20
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Sep 2024
12:40
Permit Granted
17 Sep 2024
10:20
23 Sep 2024
01:00
17 Sep 2024
10:20
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Sep 2024
16:35
Permit Alteration Granted
17 Sep 2024
10:20
27 Sep 2024
01:00
17 Sep 2024
10:20
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Sep 2024
17:09
Work Stopped
17 Sep 2024
10:20
27 Sep 2024
01:00
17 Sep 2024
10:20
27 Sep 2024
17:09
Completed

Works Permits for Stonebridge Lane, Fulbourn

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.