PARLIAMENTARY WRITTEN QUESTION
Emergency Services Network (9 October 2017)
Question Asked
Asked by:
Darren Jones (Labour)
Answer
The costs of upgrading to the Emergency Services Network and the costs to extend Airwave contracts for the emergency services are available in the public domain at:
and
Any delay in rollout impacts the date by when the savings from ESN will start to be realised. These savings will represent 50% of the cost of Airwave. The cost of delay is therefore the opportunity cost of not being able to realise the cost savings of ESN sooner.
Up to the end of 2016/17, the Programme has already delivered £77m of cash releasing benefits on existing Airwave contracts. These are benefits that would not have been obtained under the previous contractual agreements.
Answered by:
Mr Nick Hurd (Conservative)
20 October 2017
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.