PARLIAMENTARY WRITTEN QUESTION
Armed Forces: Hospitals (24 April 2017)
Question Asked
Asked by:
Rachael Maskell (Labour)
Answer
The infrastructure costs for 34 Field Hospital are not held separately. The cost of infrastructure upgrades at Queen Elizabeth Barracks, Strensall for the financial years (FY) available are set out below:
FY 2014-15 £0.7 million[1]
FY 2013-14 £0.8 million
FY 2012-13 £0.8 million
[1] Estimated due to lack of access to legacy systems.
Answered by:
Lord Lancaster of Kimbolton (Conservative)
27 April 2017
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.