PARLIAMENTARY WRITTEN QUESTION
High Speed 2 Line: South Yorkshire (17 February 2017)

Question Asked

To ask the Secretary of State for Transport, pursuant to the Answer of 1 February 2017 to Question 62120, on High Speed Railway Line 2: South Yorkshire, what the increase has been in the estimated cost of the Meadowhall route since the first estimate was made; and for what reasons that estimated cost has risen.

Asked by:
Mr Clive Betts (Labour)

Answer

The Chancellor’s Spending Review announcement in November 2015 set out an updated funding envelope of £55.7bn in 2015 prices for delivering the HS2 project. The envelope was previously £50.1bn in 2011 prices as set out in the 2013 Spending Round. The cost of building HS2 has not changed since the 2013 Spending Round, as the long-term funding envelope has simply been uprated to 2015 prices to take account of inflation. Cost estimates for specific sections of route were revised in accordance with these figures. We do not provide further funding breakdowns for specific items due to commercial sensitivities.


Answered by:
Andrew Jones (Conservative)
22 February 2017

Contains Parliamentary information licensed under the Open Parliament Licence v3.0.