PARLIAMENTARY WRITTEN QUESTION
High Speed 2 Line: South Yorkshire (27 January 2017)
Question Asked
Asked by:
Mr Clive Betts (Labour)
Answer
The financial case for Phase 2b, published in November 2016, set out that the cost of the route including Meadowhall station would be £858m higher than the option of serving Sheffield Midland station. This comparison in costs reflects estimates that have been updated for the Meadowhall route since they were originally produced.
Answered by:
Andrew Jones (Conservative)
1 February 2017