PARLIAMENTARY WRITTEN QUESTION
High Speed 2 Line (16 January 2017)

Question Asked

To ask the Secretary of State for Transport, how (a) many High Speed 2 trains per hour and (b) how long those trains would have been that served Meadowhall station under the route proposal previous to the present proposal.

Asked by:
Ed Miliband (Labour)

Answer

Our assumption was that for the previous proposal for serving South Yorkshire using Meadowhall station, up to two High Speed 2 trains per hour would have served Meadowhall to and from London and up to three to and from Birmingham. This is shown in HS2 Ltd’s Economic Case for Phase 2b (https://www.gov.uk/government/publications/hs2-phase-2b-crewe-to-manchester-west-midlands-to-leeds-economic-case, Appendix 2, p.42). These trains were assumed to be 200m trains apart from one London service of 400m.


Answered by:
Andrew Jones (Conservative)
19 January 2017

Contains Parliamentary information licensed under the Open Parliament Licence v3.0.