PARLIAMENTARY WRITTEN QUESTION
Lakes Line: Electrification (23 May 2016)

Question Asked

To ask the Secretary of State for Transport, what the expected date is for completion of the electrification of the Windermere Branch Line.

Asked by:
Tim Farron (Liberal Democrat)

Answer

In Sir Peter Hendy’s review, Network Rail has made clear that the Oxenholme to Windermere electrification scheme will be delivered, with a target of March 2017 for selection of a single option. Work is progressing on this scheme. The programme for delivery will be detailed when the single option is known.


Answered by:
Andrew Jones (Conservative)
26 May 2016

Contains Parliamentary information licensed under the Open Parliament Licence v3.0.