PARLIAMENTARY WRITTEN QUESTION
South Wales Main Line: Electrification (7 March 2016)
Question Asked
Asked by:
Stephen Doughty (Labour)
Answer
Sir Peter Hendy’s report published on 25 November 2015 stated that the electrification of the Great Western Mainline to Cardiff is planned to be completed by the end of Control Period 5, before March 2019.
Answered by:
Claire Perry (Conservative)
10 March 2016
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.