Electricity Generation: Carbon Capture and Storage (10 February 2016)
Question Asked
Asked by:
Matthew Pennycook (Labour)
Answer
Planning controls already ensure that new electricity generation facilities that emit greenhouse gases are prepared for Carbon Capture and Storage (CCS). Currently most new thermal plants larger than 300 MWe must be constructed ‘carbon capture ready’, which means they must demonstrate that it would be technically and economically feasible to retrofit CCS. Any new coal plants must be constructed with CCS fitted to at least 300 MW of their proposed generating capacity.
Answered by:
Andrea Leadsom (Conservative)
25 February 2016