PARLIAMENTARY WRITTEN QUESTION
Railways: Electrification (15 December 2015)

Question Asked

To ask the Secretary of State for Transport, what costs his Department has incurred as a result of delays to the TransPennine Midland Main Line, and Great Western Main Line electrification project.

Asked by:
Jonathan Reynolds (Labour)

Answer

The department has not incurred any additional costs as a result of Sir Peter Hendy’s re-plan of the rail upgrade programme, which includes TransPennine, Midland Main Line, and Great Western Main Line electrification.



Answered by:
Claire Perry (Conservative)
18 December 2015

Contains Parliamentary information licensed under the Open Parliament Licence v3.0.