PARLIAMENTARY WRITTEN QUESTION
M1 (4 September 2015)
Question Asked
Asked by:
Mr Toby Perkins (Labour)
Answer
The following sections of the M1 were operating at reduced speed limits on the 31 August 2015 due to roadworks taking place:
M1 J11-12, M1 J15-19, M1 J28-31, M1 J32-35a, and M1 J39-42
Project Name | Start Dates | Proposed End Dates |
A5 M1 Link (for works at M1 J11-12) | Feb 2015
| October 15 |
M1 J15-19 concrete barrier replacement | March 2014 | October 15 |
M1 J 19 improvement scheme | January 2015 | October 15 |
M1 J28-31 – concrete barrier replacement | March 2014 | December 15 |
M1 J32-35a – concrete barrier replacement | March 2014 | December 16 |
M1 J39-42 smart motorway scheme | November 2013 | February 16 |
Answered by:
Andrew Jones (Conservative)
11 September 2015