Energy: Meters (11 June 2015)
Question Asked
Asked by:
Jonathan Reynolds (Labour)
Answer
The Government has set a date of April 2016 in the licence of the Data and Communications Company (DCC) to begin operation. The Government has also made available up to six months of contingency which will be strictly governed by the Department, to enable the DCC’s systems and services to come together with the energy companies’ systems and processes in a co-ordinated start to the main installation stage. The Government has advised energy suppliers and network companies to use August 2016 as a central planning assumption for the start of DCC operations.
Answered by:
Andrea Leadsom (Conservative)
16 June 2015