Question Asked
Asked by:
Lilian Greenwood (Labour)
Answer
The Government has made no estimate of the cost of electrifying the Gospel Oak to Barking railway line. Network Rail will provide an estimate following formal sign-off of stage 3 of the Governance for Railway Investment Projects (‘GRIP’) process.
The Department for Transport has allocated £90 million towards the project (2013 prices).
Answered by:
Claire Perry (Conservative)
8 June 2015