PARLIAMENTARY WRITTEN QUESTION
Network Rail (27 May 2015)
Question Asked
Asked by:
Lilian Greenwood (Labour)
Answer
The Office of Rail and Road (ORR) reviews Control Period 5 (Rail Investment Strategy) Projects through the enhancements cost adjustment mechanism (ECAM) on a rolling basis when each project has reached a certain level of design maturity and a single option has been selected.
The ORR publishes quarterly updates on the ECAM process. These are made publicly available on its website:
Answered by:
Claire Perry (Conservative)
1 June 2015