PARLIAMENTARY WRITTEN QUESTION
Gospel Oak-Barking Railway Line (9 March 2015)
Question Asked
Asked by:
Jeremy Corbyn (Your Party)
Answer
The detailed Network Rail GRIP 3 study of the engineering works required for electrification is expected to be completed in August. This will enable confirmation of cost, scope and delivery dates. The indicative completion date of Barking – Gospel Oak electrification is June 2017 with the electrified freight links to the route being complete by December 2018.
Answered by:
Claire Perry (Conservative)
12 March 2015
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.