PARLIAMENTARY WRITTEN QUESTION
(2 September 2026)
Question Asked
Asked by:
Wendy Morton (Conservative)
Answer
Data collected in 2025 and published by the National Energy System Operator shows 72.8 GW of capacity allocated to data centres in the GB connection queue across transmission and distribution. It is not currently possible to provide a count of individual projects.
Government recently consulted on measures to manage the current oversubscription of data centre connections, which is contributing to connection delays for demand projects of all types, and will publish its response in due course.